Introduction and Contribution


American bureaucracies are frequently criticized for impeding the delivery of both public infrastructure and private development projects, wrapping them in the “red tape” of regulatory procedures. Of course, bureaucratic oversight is necessary to ensure public accountability, enable stakeholder input, and respond to market failures. It is hard to imagine how, for example, the natural environment could be protected from exploitation without regulation. Yet disagreement persists about whether the current regulatory landscape strikes the right balance between oversight and efficiency.

The National Environmental Policy Act (NEPA) of 1970 is one of the most significant federal administrative laws and is foundational to American environmental law. Per its objective of protecting the environment, NEPA requires agencies to assess the environmental impacts of major federal projects. These include construction, energy, water, and public lands projects. 

NEPA’s highest level of review is the Environmental Impact Statement (EIS), which requires substantial time and scientific expertise to complete. Accordingly, the EIS process has been criticized for causing project delays. This critique is plausible at first glance: average EIS reviews now take over four years to complete and often produce documents over 600 pages long (over 1,000 pages including appendices). 

Despite criticism over NEPA procedures, little is known about why some EISs take longer to be approved than others. Answering this question is important for assessing whether American bureaucracies can adequately balance the oversight-efficiency tradeoff.

In “A hazard analysis of federal permitting under the National Environmental Policy Act of 1970,” Michael Bennon, Daniel De La Hormaza, and R. Richard Geddes present findings on the correlates of EIS permitting. Using a dataset of nearly 1,300 EISs, the authors show that major construction projects and those occurring in states with more restrictive environmental laws are associated with longer permitting times. By contrast, privately financed projects are permitted more quickly. These findings will likely cohere with readers’ intuitions, namely that (a) more demanding regulations increase approval times and (b) private economic interests have the resources to navigate regulatory environments.

Using a dataset of nearly 1,300 EISs, the authors show that major construction projects and those occurring in states with more restrictive environmental laws are associated with longer permitting times.

The authors’ findings are relevant not only for those interacting directly with NEPA. Indeed, as illustrated in their analysis of the 2009 American Recovery and Reinvestment Act, lengthy environmental reviews can make it difficult to quickly undertake new infrastructure projects when they are needed — as was the case following the Great Recession.

Data, Methods, and Hypotheses


The authors’ dataset includes 1,269 EIS reviews. Of these, 1,161 reached a Record of Decision (ROD), the federal agency’s final decision. The average duration of time from a Notice of Intent (NOI — i.e., the intent to undertake an EIS) to ROD was 4.5 years, and the median was 3.6 years. This underscores the time required for projects to complete environmental review under NEPA.

The authors include variables for (1) major construction and infrastructure projects, which comprise about half of the data set; (2) projects backed by private investors; (3) states with restrictive environmental laws, defined, for example, in terms of whether uninjured parties can challenge projects in court or whether private actions require environmental review; and (4) inclusion in the “federal permitting dashboard,” which was created in 2015 with the goal of improving the efficiency of large projects.

To measure the correlates of EIS permitting, the authors use a “Cox proportional hazards model,” a statistical method for estimating how different variables affect the time until an event happens. For example, hazard models are often used to measure how different medical treatments affect patient mortality. For the authors’ purposes, a lower hazard rate indicates a longer permitting duration. 

The authors first hypothesize that larger projects will take longer to approve. This may be the case because such projects tend to attract greater stakeholder engagement, opposition, and litigation. Projects in states with more restrictive environmental laws, as well as those requiring supplemental EISs, are also hypothesized to take longer to approve. In addition, private financing ought to lead to faster approvals because private funders have the incentives and resources to expedite permitting. So too should the permitting dashboard decrease permitting times, consistent with its efficiency-maximizing objectives. 

Findings


As mentioned, the authors find that major construction and infrastructure projects have significantly longer permitting times, averaging 5.2 years.
 


 

Table 3 Average permit duration by phase and covariates

 

Table 4 Cox regression results for permit characteristics


Conversely, privately financed projects are indeed found to be approved more quickly, taking an average of just 3.7 years. Meanwhile, projects in states with restrictive environmental laws, such as California, New York, and Washington, are found to take longer. Contrary to the authors’ expectations, however, projects included in the federal permitting dashboard face longer permitting times. This may reflect selection bias, or the fact that projects placed on the dashboard tend to be especially large or complex. In terms of page count, longer EISs are associated with longer permitting times and longer delays. 

Finally, the authors examine permit completion rates by federal agencies, finding an average of 3 RODs per week. This rate is generally stable over time, though it spiked during Donald Trump’s election in 2016 and his inauguration in early 2017. Ultimately, the findings suggest that permitting duration is shaped not only by technical regulations but also by differences in economic resources, political conflict over projects, and federalism.

*Brief prepared by Adam Fefer.

Hero Image
Windmills on green field under white sky during daytime
Turlock Irrigation District (Turlock, CA). | American Public Power Association
All News button
1
Subtitle

CDDRL Research-in-Brief [4-minute read]

Image
Windmills on green field under white sky during daytime
Caption Turlock Irrigation District (Turlock, CA). | Photo credit American Public Power Association
Date Label
Display Hero Image Wide (1320px)
No
News Type
News
Date
Paragraphs

For the second time in history, UN Member States adopted a Political Declaration on AMR in 2024. This declaration outlines ambitious commitments to tackle one of the most pressing health challenges of our time. These commitments will only be successful if the public understands, supports, and ultimately changes behavior to make them work.

Ahead of UNGA, we asked citizens in six countries what they thought about different policy proposals across six themes: Equity, Access and Stewardship; Infection Prevention; Food Security; Awareness and Education; Target setting; and Surveillance.

Working with the Trinity Challenge, we brought together 2,419 citizens from Brazil, Colombia, Nigeria, Tanzania, India, and Indonesia using Deliberative Polling®, a method that assesses what a representative and informed sample would think about policy proposals after extended, evidence-based discussions. Deliberations took place on the innovative Artificial Intelligence (AI)-assisted Stanford University Online Deliberation Platform across two days.

Citizens left the process not just more informed, but more engaged with the solutions required.

What is Deliberative Polling® ?


Deliberative Polling® is a research methodology developed by Professor James Fishkin at Stanford University's Deliberative Democracy Lab. Unlike standard opinion polling, it measures not just initial public opinion but informed public opinion - what people think after genuine engagement with the issues, trade-offs, and expert perspectives.

It has been applied in over 160 cases around the world, from national referendums to climate policy.

Learn more about the Deliberative Polling® methodology.

"Deliberative Polling® doesn't just ask what people think - it asks what they would think if they had the chance to really engage with the evidence."
Professor James Fishkin
Stanford Deliberative Democracy Lab

Key Findings


The results were striking - and they matter for policymakers, health leaders, and the public alike.

🌍 2,419 citizens across six middle-income countries participated
📈 43 out of 45 policy proposals saw increased support after deliberation
✅ The most popular proposals were those relating to infection prevention
🌐 Regional differences emerged — particularly around attitudes to restricting antibiotic use in food production.

Antimicrobial resistance is not only a scientific challenge but a societal one. This project shows that when citizens are given balanced information, diverse perspectives, and the opportunity to deliberate, they can engage meaningfully with the complexity of AMR and support the action it requires. Building public trust and community engagement is essential to reducing the global impact of AMR. We hope these findings and resources will help advance public engagement on AMR and strengthen deliberative approaches across global health.

Support increased for 43 out of 45 proposals following deliberation. Beyond the data, participants left better informed about AMR and more engaged with the solutions on the table. That is whole-of-society action in practice.
Dame Sally Davies
Master of Trinity College Cambridge and Executive Chair of the Trinity Challenge

From Understanding to Action


This study demonstrates something important: when citizens are given the chance to engage seriously with a complex global health challenge, they rise to it.

Across all six countries, deliberation moved public opinion towards greater support for ambitious AMR action — on prescription practices, agricultural use, access to medicines, and prevention. The 2024 UN Political Declaration set out what governments have committed to. This research shows that the public, when informed, is ready to support it.

The findings have direct relevance for:

  • Policymakers designing national AMR action plans, particularly in middle-income countries
  • Health communicators seeking evidence-based approaches to public engagement on AMR
  • Researchers building the evidence base for deliberative approaches in global health
  • Civil society organizations advocating for community-level AMR action
     

We are committed to sharing these findings as widely as possible — with governments, health bodies, and the communities that took part.

Thanks to our funders


With thanks to the Novo Nordisk Foundation and Wellcome.

Contact and Media


For media inquiries and further information about the research, please contact Louise Gough (Chief Operating Officer) at info@thetrinitychallenge.org.

Read our press release.

Hero Image
Person in blue shirt washing hands
Melissa Jeanty
All News button
1
Subtitle

The Deliberative Democracy Lab and the Trinity Challenge asked 2419 people in six countries through the first-ever deliberative poll on AMR.

Image
Person in blue shirt washing hands
Photo credit Melissa Jeanty
Aria Label
Read More What Do Citizens Around the World Really Think About Tackling Antimicrobial Resistance (AMR)?
Date Label
Display Hero Image Wide (1320px)
Yes
Subscribe to Existential Risk